Fact file

Sector Domestic homes
Completed Jul 2009
Output
3kWp
Installation time
3 days
Roof type Above roof panels on concrete tiles
Panel type
Sanyo hybrid
Supplementing Solar Thermal

This solar PV system supplements the existing solar thermal installation and will take advantage of the new Feed In Tariff in 2010.

Location

Golant, Cornwall.  

Objective

The objective was to supplement the existing solar thermal installation and to take advantage of the new Feed In Tariff in 2010.

Funding

The installation has been 50% funded by the Energy Saving Trust and 50% funded by the home owner.