Mid terrace renovation
Fact file
|
|
| Sector |
Domestic homes |
|---|---|
| Completed | June 2008 |
| Output |
1.3kWp |
| Installation time |
2 days |
| Roof type | Roof integrated into slate |
| Panel type |
Sunpowered monocrystalline |
The home owner wanted to make a statement about solar power with their mid terrace renovation.
Objective
The home owner wanted to make a statement about solar power with their mid terrace renovation project.
Funding
The installation has been funded by a grant of £2,500 from the Low Carbon Building Programme (LCBP) and the home owner's own funds.